From 20.10.2020, 05.00 am to 21.10.2020, 15.00 pm the underwater concrete base of the construction pit was successfully concreted.
A coordination of approx. 375 concrete mixing vehicles was required to ensure a smooth concreting. After the base has hardened the water was pumped out in the construction pit.